|
|
 |
 |
|
|
| Potsdam WWTW -
Upgrade & Extension |
| Newsletter No
2 -
November 2007 |
 |
|
Introduction |
|
The Potsdam Wastewater Treatment Works (WWTW) is
located opposite the Caltex Oil Refinery in Table
View. In response to the significant development
occurring in the Blaauwberg Area, the City of Cape
Town identified the need to upgrade and extend the
Potsdam WWTW. Environmental approval was obtained in
December 2002, authorising the proposed activities.
Interested and Affected Parties (I&APs) subsequently
appealed against Department of Environmental Affairs
and Development Planning’s (DEA&DP) decision.
Accordingly the then acting MEC of Environmental
Affairs reviewed his Department’s Record of Decision.
The MEC issued his ruling on 27 June 2003 in which
he upheld the original Record of Decision, with
various modifications to the Conditions of Approval. |
 |
|
Construction activities
at the Potsdam WWTW
commenced towards the
end of 2004, and
considerable progress
had been made since
then. In light of the
keen public interest
attached to this
project, both during the
Environmental Impact
Assessment (EIA) process
and since the initiation
of construction, the
first Potsdam Newsletter
was circulated in March
2006 to update the I&APs
with of the project’s
progress. This second
publication serves as a
further progress update
on the future
development of the
project. |
|
|
 |
|
General |
|
The upgrading and extension of the Potsdam WWTW
comprises various improvements to some of the
existing facilities and a capacity increase from 32
mega litres per day (Mℓ/d) to 47 Mℓ/d. The works are
currently receiving approximately 35 Mℓ of
wastewater daily. |
|
The additional 8 Mℓ interim
capacity plant was commissioned
in August 2007 and has
alleviated dependency on the
existing biofilter plant,
thereby improving the overall
quality of effluent leaving the
plant. Construction for the
Phase II Main Extension of the
works is progressing well and is
on track towards providing the
full 47 Mℓ/d plant by April
2008. The following sections
provide a more detailed overview
of the key components of the
upgrades currently being
undertaken on site. |
|
 |
|
Interim Capacity Plant |
|
Since it was anticipated that the proposed
activities at Potsdam WWTW would take the better
part of four or five years to complete, the City and
its consulting engineers devised an approach to
construction where an additional 8 Mℓ/d could
temporarily be provided to relieve pressure from the
existing process capacity. Once the main extension
is commissioned the interim capacity plant will fall
away and its structures will be modified to serve as
aerobic digestors instead. From this point the
biofilter plant will no longer be used. |
 |
The interim capacity contract is
currently in its maintenance
period which will continue until
August 2008. The works’ staff
and engineer are working
together to achieve the
operating conditions that will
treat the effluent to Department
of Water Affairs and Forestry
(DWAF) standards. It is expected
that the correct balance meeting
these standards will be
established shortly. |
|
|
|
|
|
Figure 1: Effluent from Interim
Capacity plant, October 2007. |
|
 |
|
Disinfection of Final Effluent |
|
The Final Scoping Report for the Potsdam WWTW
reported that the Ecoli present in the final
effluent leaving the WWTW significantly exceeded the
standards set by DWAF. Although the impact of this
on Rietvlei and the Diep River must be
contextualised against the background of the poor
quality of water travelling down the Diep River and
entering the Milnerton Lagoon from the Theo Marias
stormwater outfall and other sources, the City
recognised that this was unacceptable and
accordingly provided for the disinfection of the
final effluent. |
|
The contract for disinfection of
the final effluent from the
works was completed in February
2007. The system uses a set of
lamps which emit ultraviolet
radiation into the effluent
stream to neutralize any
bacteria present. The
effectiveness of this treatment
is dependant on the effluent
clarity which is measured using
a transmissivity index (UVT).
The Ecoli are removed to within
acceptable limits when the
effluent has a UVT of 45%. A
portion of effluent,
approximately 30%, is still
treated through the biofilter
plant with the result that the
overall effluent clarity is less
than ideal. Once the main
extension of Potsdam WWTW is
commissioned and the biofilters
are decommissioned the overall
effluent UVT is expected to
exceed 45% which will lead to
excellent disinfection
performance within the permitted
limits (set at 1000/100ml). |
 |
|
Figure 2: Ultraviolet treatment
of final effluent. |
|
 |
|
Table View East Odour Control
Biofilter |
|
During the EIA process concerns were raised by the
various I&APs, regarding odours emanating from the
works. In light of these concerns, amelioration of
this impact was prioritised by the City and a
comprehensive approach to odour control was adopted. |

Figure 3: Odour control
biofiltration plant at the Table
View East pumpstation |
The first phase of the odour
control strategy was implemented
at Tableview East Pumpstation, a
prime source of odours at
Potsdam WWTW. The pumpstation is
located on the banks of the Diep
River, opposite a residential
area. The pumpstation was sealed
and air extracted through a
dedicated biofiltration plant.
The biofilter contains bacteria
which remove odorous compounds
from the air stream before it is
released to atmosphere. |
|
The contract for odour control
at the Tableview East Pump
Station was completed in August
2007 with the biofilter
successfully achieving the
specified treatment levels. The
plant was evaluated in four
quarterly tests over a one year
period which started in August
2006. The performance of the
biofilter was calculated by
measuring the hydrogen sulphide
(H2S) levels in the inlet and
outlet air streams. |
|
The odour control biofiltration
plant was initially fed by
treated effluent to humidify the
biofilters. At one point the
department controlling the
effluent reuse introduced
hypochlorite into the effluent
stream to prevent algae growing
in their pipelines and filters.
This hypochlorite effectively
poisoned the bacteria in the
biofilters. It took some time to
determine the cause of the
problem, at which point we
reverted to using potable water
in the humidification process.
Having switched to potable water
it took a further month or two
for the biofilters to recover to
their normal balance. |
|
It should be noted that the
Table View East pumpstation
odour treatment facility is only
one of the planned odour
abatement measures. Pursuant to
the completion of the main
extension, a main odour
treatment contract will be
implemented to deal with the
off-gases from the other
odour-producing sites which
include the new inlet works, the
new and existing primary
settling tanks and the new
sludge dewatering facility.
Moreover, the decommissioning of
the biofilter works will also
reduce odours as these are open
to the atmosphere. |
|
 |
|
Electrical Supply Upgrade |
|
Work has been completed on the medium voltage
electricity supply to the works which is now on a
ring main ensuring that power to any part of the
plant is not interrupted should a portion of the
supply cable require maintenance. |
|
Furthermore, there is now a
standby electrical generator on
site which allows the Tableview
East pump station and the UV
disinfection facility to
function independently in the
event of a power failure. A
generator is also planned to
provide emergency power to the
new inlet works and raw sewage
pump station. These generators
will ensure that critical
processes can operate at all
times and that the risk of
overflowing under power failure
conditions will be dramatically
reduced. |
|
 |
|
Budget |
|
The project is now in its fifth year with a total of
R150 million of the budget having been spent thus
far. This represents 64% of the total budget
available for the six year project. There are a
number of contracts currently under preparation or
out to tender that will further upgrade the works as
follows: |
|
• |
The construction of a new
dewatering plant to increase the
sludge handling capacity of the
plant. |
|
• |
The construction of a new inlet
works to increase and improve
the screening process. |
|
• |
The installation of odour
control measures as part of the
current main extension contract. |
|
• |
The installation of a further
generator as a contingency in
the event of power failure. |
|
 |
|
Environmental Considerations |
|
The Record of Decision issued by DEA&DP attached
various conditions to the authorisation. Most
importantly, the City of Cape Town was required to
keep I&APs informed by constituting an Environmental
Monitoring Committee (EMC) and to develop and
implement an Environmental Management Plan (EMP) for
the construction phase: |
|
• |
The Potsdam EMC was constituted
in July 2004, and comprises the
following: |
|
» |
City of Cape Town; |
|
» |
Ward Councillors; |
|
» |
Friends of Rietvlei; |
|
» |
Table View Residents
Association; |
|
» |
Milnerton Residents Association; |
|
» |
Milnerton Ridge Residents
Association; |
|
» |
Parklands Homeowners
Association; |
|
» |
Wildlife and Environment Society
of South Africa; |
|
» |
Representative for developers; |
|
» |
Representative for effluent
re-users; |
|
» |
DEA&DP; |
|
» |
The Department of Water Affairs
and Forestry (DWAF); and |
|
» |
The Environmental Control
Officer (ECO), who also acts as
Chair and fulfils the
secretarial functions of the
EMC. |
|
The role of the EMC is to
monitor and report to the City
of Cape Town, DEA&DP, DWAF and
their organisational
constituents on the construction
activities associated with the
upgrading and extension of the
Potsdam WWTW, in terms of the
environmental requirements set
in the Record of Decision and
the EMP. Since its constitution,
the EMC has held 14 meetings,
the frequency of which has been
dictated by the EMC members. |
|
As per the requirements of the
Record of Decision, an EMP was
compiled and approved by the
DEA&DP. The EMP takes the form
of a series of environmental
specifications that are
integrated into Tender
Documentation for each contract. |
|
ANA were appointed as the
Environmental Control Officer
(ECO) for the construction
phase, and are responsible for
monitoring day-to-day compliance
by the various Contractors with
the requirements of the EMP. The
ECO reports on a monthly basis
to the City of Cape Town, the
EMC and DEA&DP. As per the
requirements of the Record of
Decision and good practice, the
ECO and EMC will continue to
monitor compliance with the
environmental requirements. |
|
[ANA is a joint venture
comprised of ASCH, Ninham Shand
and Africon. Michael Mangnall
and Tinka Shapiro from the
Ninham Shand Environmental
Discipline Group are acting as
the ECO.] |
|
 |
|
The Way Forward |
|
The Phase II Main Extension of the activated sludge
works is on programme for completion in April 2008.
This will see a dramatic improvement in the quality
of the effluent produced by Potsdam WWTW and will
increase the capacity of the plant to 47 Mℓ/d. |
|
Next Year (2008) will be a busy
year at Potsdam WWTW with a
number of contracts to be
awarded before the year end that
will culminate in completion of
the project in April 2009. |
|
Interested and affected parties
will be kept informed on a
quarterly basis by projects
newsletters issued by the City
of Cape Town. However, should
more frequent or detail
information be required, I&APs
should feel free to contact
their representatives on the EMC
or the ECO (Michael Mangnall or
Tinka Shapiro Tel: 021 481
2400, Email:
enviro@shands.co.za). |
|
 |
|
|
 |
|
Click
here to view Newsletter No 3 - November
2008 |
 |
|
 |
|
|
|
|